2023-11-13 - Commercial Order - Argeo formally signs contracts for three KONGSBERG HUGIN AUVs
- The contracts were signed on 13 November 2023 at KONGSBERG premises in Horten. The order comprised two HUGIN Superior AUVs and one HUGIN 6000, financed through CSI Leasing. -
source: argeo.no
2023-09-11 - Commercial Order - Argeo orders HUGIN AUV fleet expansion from Kongsberg
- The order covered two HUGIN Superior AUVs and one HUGIN 6000 delivery sequence. The fleet expansion increased Argeo subsea survey operating capacity. -
source: offshore-energy.biz
2023-04-25 - Contract Award - Argeo extends HUGIN 6000 AUV project to March 2024
- The extension carried a minimum initial value of $2 million. The project had started in September 2022 and continued with added AUV utilization. -
source: argeo.no